Sample-to-production timeline planner

Plan the Known Working-Day Sequence

Add your internal approval time and a planning buffer. The result keeps NEXO sample preparation, international sample delivery and commercial production as separate stages.

For the related manufacturing scope and project requirements, see Cosmetics Export Manufacturing Support.

Known working-day subtotal

25-32 working days
Sample preparation 3 days
Sample delivery 5-7 days
Your approval 5 days
Production 10-15 days

The 2-day planning buffer is added after the four named stages.

The subtotal is not a promised launch date. Formula revisions, extra sample rounds, packaging availability, holidays, customs, market review and carrier acceptance are outside the fixed base stages unless you add them to your own approval time or buffer.