Sunscreen Launch Critical Path Planner
Sunscreen Launch Critical Path Planner
Model a planning path from samples through testing, packaging and production. Testing and packaging are shown in parallel after sample approval; the result is a planning estimate, not a delivery promise.
For the related manufacturing scope and project requirements, see Sunscreen Manufacturing.
Sample path
28 daysParallel test/pack path
35 daysProduction path
35 daysPlanning total: 98 days
Packaging is the longer parallel path in this scenario.