Three of the four stages between a brief and finished goods are ours, and they are committed in writing. The fourth is yours: how fast samples come back approved, and how early the packaging decision lands. Set those two and the tool counts the whole programme.
For the related manufacturing scope and project requirements, see NEXO cosmetic manufacturing.
Your Side of the Programme
Set your requirements below to calculate the critical path.
Programme Analytics Result
Pending input… Set your rounds, review days and packaging lead time, then select “Count The Programme”.
Committed Stages We Hold
Our fixed turnaround metrics.
| Stage | Committed | Counted from |
|---|---|---|
| First sample preparation | Within 3 working days | Receipt of your product brief |
| International sample delivery | 5–7 working days | Sample dispatch, by destination |
| Commercial production | 10–15 working days | Formula approval and packaging confirmation |
Why Packaging Usually Decides the Date
Sampling and packaging procurement run alongside each other, so the longer of the two sets the start of production. Confirming components late is the single most common reason a launch date moves, and no amount of production speed recovers it.
- Sample rounds each carry preparation, courier time and your own review
- Packaging lead time runs in parallel, not after
- Production only starts once formula approval and packaging confirmation are both in
- Sample approval is required before every production run, without exception